Modelled ports

Examples of preliminary port modelling

Selected examples of ports preliminarily modelled using public call data; indicative estimates, not completed client engagements or endorsements.

Spain

Valencia

Annual energy
192.6GWh
Mean
22.0MW
P95
32.1MW

Large, steady container base load with an evening ferry peak — power planning is driven by a high floor, not just the peak.

Discuss Valencia

Spain

Las Palmas

Annual energy
83.9GWh
Mean
9.6MW
P95
15.7MW

A mixed fleet of container, ferry and tanker calls spreads demand across the day.

Discuss Las Palmas

Spain

Palma de Mallorca

Annual energy
65.6GWh
Mean
7.5MW
P95
23.7MW

Cruise-driven daytime peaks: hourly peaks and phasing need as much attention as annual energy.

Discuss Palma de Mallorca
Assess my portStart with a short enquiry

How to read these figures. Annual energy is the shore power vessels at berth would draw over a year. Mean is the average hourly demand. P95 is the level not exceeded in 95% of hours — a planning threshold, not a grid design.

Scenario: 2025 · mid power · full adoption. Source: Bridge Power working model v0.2.1 (built 2026-11-10), modelled from public ship-call records. Vessel figures are category estimates, not measured energy or customer results. Ports are listed for illustration and are not ranked.